U.S. Nuclear Weapons Stockpile, July 1996
U.S.
nuclear forces after START II (2003) table
Little change occurred over the year in the size of
the U.S. nuclear stockpile, though we have new understandings
of its future direction and composition. Regardless of whether
START II is fully implemented, the total number of warheads in
all categories will remain between 9,500 and 10,000. If START
II is implemented and strategic nuclear force reductions are
made, the only difference will be in the ratio of warheads
deployed to those in a less-ready condition.
Warheads now fall into one of four categories: (1)
those assigned to active delivery systems; (2) "hedge"
warheads in storage that could be redeployed quickly to
increase forces back to START I levels; (3) "inactive reserve"
warheads in a less-ready condition that could be used to
replace stockpiled weapons withdrawn for testing and as a
source of spare parts; and (4) retired warheads awaiting final
disassembly at Pantex in Texas.
The "enduring" stockpile. The operational U.S.
nuclear stockpile-those warheads that accompany deployed
forces-has now stabilized, and without progress on START II it
is unlikely to decline any further. The table on page 63 is
our estimate of the composition of the current operational
stockpile of approximately 9,250 warheads. Assuming that START
I and II will be fully implemented, the operational stockpile
in the year 2003 is scheduled to be 5,000 warheads, composed
of some 3,500 strategic and 950 non-strategic weapons, plus
about 500 spares (see the table at right). This total will be
split in half between the air force and the navy, with 79
percent overall in strategic forces.
Supplementing those in the field will be another 2,500
warheads in the "hedge," a category created by the 1994
Nuclear Posture Review. These warheads will be removed from
delivery systems under the requirements of the START treaties,
but could be redeployed onto missiles and aircraft. The hedge
is discussed in greater detail in the July/August 1995 Nuclear
Notebook.
When he signed the Nuclear Weapons Stockpile Memorandum
on February 23, 1996, President Bill Clinton directed that the
Defense Department not make any unilateral reductions beyond
those required by START I.
The inactive stockpile. Another set of warheads
are in the inactive reserve. They are stored in military
depots and thus not scheduled to be disassembled at the Pantex
plant. If and when START II is implemented, the inactive
stockpile will also contain some warheads now in the
operational stockpile that will be withdrawn. We estimate that
the inactive stockpile will eventually contain 2,500 to 3,000
warheads.
The requirement for an inactive stockpile stems from a
U.S. policy that warheads in the enduring stockpile be
maintained with sufficient tritium to achieve their design
yield at all times. This is not the case with warheads in the
inactive reserve. While they remain intact, their tritium is
removed. Thus the inactive reserve warheads require more time
to be readied for redeployment. The W84 warheads retrieved
from the eliminated ground-launched cruise missile are the
only type now in the inactive stockpile, but others are in
transition to it. See the table below.
Retired warheads awaiting dismantlement. In the
fourth category are "retired" warheads removed from
operational service that are awaiting their turn on the
disassembly line. The warheads to be disassembled over the
next three years (through mid-1999) include the W79 army
artillery warheads, the W55 for the SUBROC (submarine rocket),
the W69 for the SRAM-A (short-range attack missile), the W56
Minuteman II warhead, and B61 Mod-2 and Mod-5 bombs. The W48
artillery shell (March 1996), the B61 Mod-0 bomb (June 1996),
and the W70 for the Lance (February 1996) are warheads for
which disassembly has been completed, or is nearly
complete.
In October 1992, the Energy Department set a
dismantlement goal of 2,000 warheads per year. It never
reached that level. The workload goal decreased with the
creation of the hedge and inactive reserve-so much so that
under current schedules, Pantex will cease dismantlement work
in fiscal 1999.
The actual and projected rates of dismantlement and
disposal are listed below:
|
Year |
Warheads |
|
1990 |
1,154 |
|
1991 |
1,595 |
|
1992 |
1,856* |
|
1993 |
1,556 |
|
1994 |
1,369 |
|
1995 |
1,393 |
|
1996 |
1,166 |
|
1997 |
1,221 |
|
1998 |
1,084 |
|
1999 |
415 |
* Includes 553
uranium-only W33 warheads dismantled at the Y-12 plant at Oak
Ridge, Tenn.
On January 19, 1994, Energy announced a decision to
increase plutonium "pit" storage at the Pantex plant from
about 6,000 to some 12,000 to accommodate dismantled weapons.
According to a Pantex spokesman, as of April 30, 1996, there
were 8,874 pits in storage. Under current schedules, by
September 30, 1999, when dismantlements end, there will be
approximately 12,000 pits in storage in Texas.
After the backlog of retired warheads are disposed of,
Pantex will continue to perform evaluation work on a small
number of warheads each year. During evaluation some warheads
are not, or cannot, be put back together and they are disposed
of. Others are evaluated, then reassembled and returned to the
stockpile. The United States uses approximately 60 warheads
per year in evaluation and disposal. In the 1980s, when the
stockpile was larger and there were more types, twice as many
warheads on average were disposed of during evaluation. In the
evaluation/reassembly category, the average number during the
1990s is 69 per year; in the 1980s it was 210 per
year.
The post–START II stockpile- operational, hedge, and
inactive reserve-will comprise ten warhead types, with Los
Alamos responsible for the stewardship of six types (B53, B61,
W76, W78, W80, W88) and Lawrence Livermore responsible for the
stewardship of four (W62, W84, W87, B83). Some types will be
in more than one category, while others will be in only
one.
Development of new capabilities. In the
near-term, the laboratories are working on alterations to the
B61 bomb, a B83 quality improvement program, a W76 neutron
generator replacement, a W76 tritium reservoir replacement, a
W87 life-extension program, W88 pit rebuilding, and the
B61/B83 common radar program.
Last September, the Los Alamos Study Group, a Santa
Fe-based watchdog, revealed that work was being done toward
modifying a B61 bomb for improved earth-penetrating
capability. The U.S. government went to great pains at the
time to insist that the bomb, if deployed, would not
constitute a new nuclear weapon, and public talk of the
modification ceased.
But this April, Defense Department spokesman Kenneth
Bacon confirmed that the United States was modifying existing
bombs (presumably the B61) to attack deeply buried targets.
Admittedly, this is in lieu of a new earth-penetration
warhead, long on the design boards of nuclear scientists. It
also was discovered that in fiscal 1995, the air force
undertook a second program to develop a B61 Mod-11 nuclear
bomb- an improved older B61-customized for strategic
bombers.
In 1995, the air force also initiated the Single
Reentry Vehicle (SRV) program. The program's purpose is to
coordinate air force and navy reentry vehicle (RV) research,
to monitor performance of existing ballistic missile reentry
vehicles, and to design an improved RV for the future. In the
words of Paul Kaminski, undersecretary of Defense for
Acquisitions and Technology, such a new system would, "deal
with new classes of targets-i.e., deep, hardened and/or
relocatable targets." With MX W87 warheads already in hand,
the air force apparently does not seem interested in designing
a new warhead for this prospective RV, yet the May 9 issue of
Inside the Pentagon revealed navy interest in investigating a
back-up warhead design for its SLBMs.
A number of special studies also continue to be
conducted by the Energy Department and the Defense Department,
particularly for newer designs that might improve long-term
safety (like an all-uranium warhead) or "tailored" effects
weapons with specialized war-fighting missions. For instance,
the Phase 2 study for the high-powered radio-frequency warhead
was completed in 1995, and the design was fully documented and
placed on the shelf. Despite the demise of the so-called
"mini-nukes" program, various warhead ideas to counter weapons
of mass destruction are also being investigated by the nuclear
laboratories and the air force.
Continuing nuclear costs. Despite no new nuclear
warhead production since 1990, delivery of the eighteenth and
final Trident submarine in 1997, and completion of B-2 bomber
production in 1998, the cost of modernizing and maintaining
the nuclear force continues to be sizable. Energy is scheduled
to spend $20 billion in the Stockpile Stewardship Program over
the next five years, an amount that exceeds the average annual
level of Cold War spending on nuclear warhead research,
development, testing, and production. Meanwhile, Defense has
undertaken a $4.5 billion D5 backfit program to equip 14
ballistic missile submarines, instead of only 10, with Trident
II missiles, claiming it must maintain an industrial base to
build ballistic missiles.
Operation and maintenance costs of the ICBM force,
including procurement of minor missile-related items, is
estimated at $5.7 billion through the life of the current
force (until 2020), according to the proposed 1997 budget.
Pentagon spending on more major upgrades and replacement
programs adds up to approximately $10 billion (see below).
This does not count procurement of such systems as a new RV,
mentioned above, or new strategic command, control, and
communications equipment. Here are some of the programs and
their costs:
Trident D5 Navigation Upgrade, $250 million; Minuteman
III Propulsion Replacement, $2.9 billion; Minuteman Guidance
Replacement, $1.6 billion; Air Force/Navy RV Upgrade Studies,
$250 million; ICBM and SLBM day-to-day upkeep, $3 billion; B-2
day-to-day upkeep, $1 billion.
(The last three items only show costs through the end
of the current five-year defense plan.)
Referring to these ongoing efforts, air force Gen.
Eugene E. Habiger, commander of U.S. Strategic Command,
testified before the Senate in March that, "other sustainment
and modernization programs in each leg of the Triad will be
needed to preserve our technological edge over the next 30
years."
U.S. nuclear forces after
START II, 2003
| |
|
|
Warhead type |
Warhead number |
Operational |
| Strategic
forces |
|
|
|
|
| ICBMs |
500 |
Minuteman II |
W87-0, W78, W62 |
500 |
| SLBMs |
336 |
Trident II on 14 SSBNs X5 |
W76 W88 |
1,280 400 |
| Bombers |
21 32 32 |
B-2A Spirit, B-52H x 20,
} B-52 x 12 |
B53, B61-7,
-11 B83 W80-1 |
400 500 400* |
Subtotal |
~3,500 |
| Non-strategic forces |
|
|
|
|
| Sea-launched cruise missiles |
|
W80-0 |
350 |
| Air force tactical bombs |
|
B61-3, -4, -10 |
600 |
Subtotal |
950 |
| Total operational warheads |
5,000** |
"Hedge" |
| ICBM warheads (W62, W78) to upload
Minuteman IIIs |
2,500 |
| SLBM warheads (W76) to upload Trident
missiles |
| Bomber weapons for B-1 and B-52H |
Inactive (tritium removed but intact) |
| B61 bombs, W62 ICBM
warheads, W76 SLBM warheads, W80 ALCM warheads, and W84
GLCM warheads |
2,500 |
| Grand Total |
~10,000 |
*The
advanced cruise missile (ACM) is currently planned to be
carried only by the B-52.
**Number includes spares for
routine maintenance.
Operational U.S. nuclear
weapons stockpile, July 1996
| Warhead/weapon |
First produced |
Yield (kilotons) |
User |
Number (warheads) |
Comments |
| Bombs |
| B53-1 |
8/62 |
9,000 |
AF |
50 |
Will be retained. |
| B61 Strategic |
10/66 |
10 to 300 |
AF |
750 |
Mod-7 is the only version in
the strategic stockpile It is a converted Mod-1 with CAT
D PAL and IHE. |
| B83/B83-1 |
6/83 |
low to 1,200 |
AF |
650 |
Strategic bomb replaced B28,
B43, and B53. |
| Submarine-launched ballistic
missiles |
| W76/Trident IC4 |
6/78 |
100 |
N |
3,000 |
Over 1,500 W76 warheads from
retired Trident I SLBMs are available for Atlantic Fleet
Trident II SLBMs. 1,000 less will be needed if START II
is implemented. |
| W88/Trident II D5 |
9/88 |
475 |
N |
400 |
Warheads will supplement the
W76 warhead and arm Atlantic Fleet Trident II
SSBNs. |
| Intercontinental ballistic missiles |
| W62/Minuteman III |
3/70 |
170 |
AF |
610 |
In a reversal from the Nuclear
Posture Review, W62 warheads will be retained. |
| W78/Minuteman III |
8/79 |
335 |
AF |
920 |
Some may be used to arm
single-warhead Minuteman IIIs. |
| W87-0/MX |
4/86 |
300 |
AF |
525 |
Missile will be retired and
W87 used for a single-warhead Minuteman III if START II
is implemented. |
| Air-launched cruise missiles |
| W80/-1ACM |
?/90 |
5 and 150 |
AF |
400 |
Operational in 1991. Original
program of 1,461 ACMs has been cut to 460. Uses W80
warheads from ALCMs. |
| W80-1/ALCM |
12/81 |
5 and 150 |
AF |
1,000 |
Some 50 exist as conventional
versions (CALCM). It is planned that more ALCMs will be
converted to CALCMs. During the Persian Gulf War, 39
CALCMs were launched. Some 700 ALCMs are in storage with
their warheads removed. W80s are used to arm ACMs. |
| Non-strategic forces |
| B61 tactical bomb |
3/75 |
0.3 to 170 |
AF, NATO |
600 |
Mods-3, -4, -10. The Mod-10 is
a converted W85 Pershing II warhead. All have CAT F PALs
and IHE. Each Mod has four yield options: The B61-3
(0.3, 1.5, 60, and 170 kilotons), the B61-4 (0.3, 1.5,
10, and 45 kilotons), and the B61-10 (0.3, 5, 10, and 80
kilotons). |
| W80-0/SLCM |
12/83 |
5 and 150 |
N |
350 |
Nuclear SLCMs now stored
ashore. Original program of 758 for 200 ships and
submarines reduced to 367 SLCMs, now for 25
Sturgeon-class, 62 Los Angeles-class, and 3
Seawolf-class attack
submarines. |
AF: Air Force; N: Navy; NATO: non-U.S. delivery system;
ACM--advanced cruise missile; ALCM--air-launched cruise
missile; IHE--insensitive high explosive; PAL--permissive
action link; SLBM--submarine-launched ballistic missile;
SLCM--sea-launched cruise missile; SSBN--nuclear-powered
ballistic missile submarine. In weapons nomenclature B stands
for "bomb" and W for "warhead." The number following the
letter indicates the order in which it was introduced into the
stockpile; for example, W88 followed W87.
Nuclear Notebook is prepared by Robert S. Norris and
William M. Arkin of the Natural Resources Defense Council.
Inquiries should be directed to: NRDC, 1200 New York Avenue,
N.W., Suite 400, Washington, D.C., 20005; 202-289-6868.